Taking charge of EV infrastructure changes

One of the most significant barriers to the rollout of EV chargers has been the cost of connecting to the grid.

One of the most significant barriers to the rollout of Electric Vehicles (EV) chargers, and particularly rapid and ultra-rapid chargers (50 kW and above), has been the cost of connecting to the grid. Such costs vary from thousands to millions of pounds, based on the required network reinforcements that typically relate to the age of the network, the load it was designed for, and the existing demand profile. 

Different levels of power network constraints across the country lead to network access challenges that create a ‘postcode lottery’ for public EV charger rollout. Constraints can be very localised and differ from street to street. While programs like the Green Recovery Fund, the Rapid Charge Fund, and the Local Electric Vehicle Infrastructure scheme seek to offset certain costs of transitioning to a zero-emission future on a project-by-project basis, a new Ofgem ruling offers a more holistic solution. 

From 1st April, Distribution Network Operators (DNO) may no longer pass network reinforcement costs through to the connection customer, except for any proportion above the 'high-cost cap' threshold of £1,720 per kVA (very few connections exceed this threshold). Network reinforcement costs are those that relate to the upgrading of network assets, such as transformers and cables, upstream of the connection. Costs associated with the extension of the network to the point of connection will still be charged to the connection customer.

What will this change mean for the rollout of EV charging infrastructure? Developers will be able to apply to connect and rollout chargers at sites that were previously prohibitively expensive. There will no longer be such a disparity in the cost of connections to the electricity network at different locations. 

In anticipation of this new ruling, developers have been holding off on their connection applications, and DNOs are bracing for a surge of new connection requests from April. This will inevitably push already lengthening lead times for quotations and indeed for the subsequent delivery of network infrastructure (for connections 1,000 kVA and above – equivalent to 20 rapid or 6 ultra-rapid charger – typical connection times are six months and above), in an environment where DNOs already face a deepening national skills shortage in engineering.

To alleviate the impact of their growing resource challenge for customers, DNOs like SP Energy Networks, Northern Powergrid and National Grid are starting to offer online, self-serve budgeting tools giving visibility into the network’s physical location and available capacity.  These allow customers to quickly and directly consider both placement of prospective EV charging infrastructure and high-level cost estimates.

The UK’s electricity distribution networks will require time, additional skilled resources, and funding to accommodate our national shift to electrified transport. While this new Ofgem ruling will reinforce other government programs in mitigating the direct impact of infrastructure investments on EV charging providers and their customers, DNOs will need to continue to streamline their processes for accelerating infrastructure development.

Off

Subscribe to our newsletter, The Edit

We are Steer

Yes, you are in the right place. After 40 years, we have changed our name from Steer Davies Gleave to mark our growing international footprint and our expanding portfolio into sectors beyond transport.

Explore our new website to learn more about Steer: who we are, how we work and what our future holds.

Related insights

  • 22 Oct 2025
    Article

    Game Changers: The megatrends that will redefine global infrastructure

    Jon Peters
    Associate Director

    Our latest global insight report exploring the forces transforming how we move, power, and connect the world.

    Read more

  • 24 Sep 2025
    Article

    Steer brings ninth annual Local Transport Summit to the East Midlands

    By Steer

    Steer is proud to sponsor the 2025 Local Transport Summit in Derby, driving vital discussions on devolution and future transport.

    Read more

  • 18 Sep 2025
    Article

    Ancoats Mobility Hub: Enabling car-lite developments

    By Steer

    Steer supported the UK’s first purpose-built Mobility Hub with commercial modelling to enable sustainable, car-lite regeneration.

    Read more

  • 01 Sep 2025
    Article

    Ropeways in India and what to expect

    Samhita Indurkar
    Associate

    India’s ropeway network is expanding fast. We explore key drivers, funding models, and future potential.

    Read more

  • 31 Jul 2025
    Article

    New study shows best ways to unlock value of UK railway station estate

    Richard Harper
    Director

    Steer and RIA outline strategies to unlock station potential, creating sustainable, connected hubs that drive social and economic value.

    Read more

  • 09 Jul 2025
    Article

    What makes for ‘good’ deliveries on the high streets of the UK?

    Fiona Jenkins
    Associate Director

    Deliveries are vital to city life. Steer helps design practical, people-first freight solutions for vibrant streets.

    Read more

  • 04 Apr 2025
    Article

    How is EV doing in Europe’s Big Five economies?

    As Europe accelerates towards a zero-emission future, what’s really driving EV adoption—and what’s holding it back?

    Read more

  • 28 Feb 2025
    Article

    Planning transport for the next generation of New Towns: Vertiports or cycle lanes?

    Profile image
    Matthew Clark
    Associate Director
    Jon Williams
    Associate Director

    As the Labour Government eyes its 1.5 million housebuilding target, how can we ensure these communities work for the future?

    Read more

  • 07 Feb 2025
    Article

    ZEV Mandate – How’re we doing? - Penetration of EVs within the UK’s vehicle parc

    First in the Ramping Up series, this article explores the realities of EV market growth and its impact on key sectors.

    Read more

  • 24 Jan 2025
    Article

    What does 2025 have in store for infrastructure investors? Here is Steer’s outlook

    Antonio Beltrán Arranz
    Associate

    Steer’s Antonio Beltran Arranz explores key investment trends for 2025, from rail modernisation to renewable energy growth.

    Read more

  • 09 Dec 2024
    Article

    What did we learn at the Local Transport Summit 2024?

    By Steer

    Another successful Local Transport Summit saw Steer along with industry professionals from across the board congregate in Bedford this week.

    Read more

  • 02 Dec 2024
    Article

    Is integrated transport planning and housing development the key to achieving multiple policy goals?

    Steven Bishop
    Director

    How can sustainable transport and planning shape the future of housing and communities?

    Read more